Projects / SR-AHB-003
Hospitality · Abha · Asir Hospitality Group
Abha Highlands Resort
PM Khalid Al-Shehri · 2025-03-18 → 2027-02-28
Health score
70
Progress
41%
Plan 47%
Contract value
SAR 274M
Cost to date
SAR 121M
44% of budget
Workers today
263
Open risks
9
Milestones
- Mobilisation & enabling worksMar 2025
- Substructure completeAug 2025
- Superstructure 50%Jan 2026
- Building envelope closedJul 2026
- MEP testing & commissioningFeb 2027
- HandoverJun 2027
AI insights
SR-AHB-00374% conf.
Labour productivity down 14% this week
Facade crew output fell from 42 to 36 m²/day. Weather and late scaffold handovers are likely causes.
Recommended: Add second scaffold crew and shift facade work to morning hours.