Projects / SR-DMM-008
Residential · Dammam · Gulf Living Holdings

Dammam Coastal Villas

PM Sara Al-Qahtani · 2024-11-05 → 2026-05-20

On Track
Health score
88
Progress
72%
Plan 74%
Contract value
SAR 96M
Cost to date
SAR 66M
69% of budget
Workers today
148
Open risks
3

Milestones

  1. Mobilisation & enabling worksMar 2025
  2. Substructure completeAug 2025
  3. Superstructure 50%Jan 2026
  4. Building envelope closedJul 2026
  5. MEP testing & commissioningFeb 2027
  6. HandoverJun 2027

AI insights

No active AI alerts. Project signals are within normal range.