Projects / SR-JED-022
Logistics · Jeddah · Red Sea Freight Co.
Jeddah Logistics Hub
PM Omar Bakr · 2025-06-01 → 2026-12-15
Health score
61
Progress
34%
Plan 45%
Contract value
SAR 188M
Cost to date
SAR 79M
42% of budget
Workers today
212
Open risks
12
Milestones
- Mobilisation & enabling worksMar 2025
- Substructure completeAug 2025
- Superstructure 50%Jan 2026
- Building envelope closedJul 2026
- MEP testing & commissioningFeb 2027
- HandoverJun 2027
AI insights
SR-JED-02287% conf.
Steel delivery delay threatens roof milestone
PO-2291 structural steel is 11 days behind. Critical path shows roof enclosure slipping 9 days if not recovered.
Recommended: Expedite alternative supplier quote (Al Jazira Steel) and resequence MEP rough-in.