AE
Projects / SR-JED-022
Logistics · Jeddah · Red Sea Freight Co.

Jeddah Logistics Hub

PM Omar Bakr · 2025-06-01 → 2026-12-15

Delayed
Health score
61
Progress
34%
Plan 45%
Contract value
SAR 188M
Cost to date
SAR 79M
42% of budget
Workers today
212
Open risks
12

Milestones

  1. Mobilisation & enabling worksMar 2025
  2. Substructure completeAug 2025
  3. Superstructure 50%Jan 2026
  4. Building envelope closedJul 2026
  5. MEP testing & commissioningFeb 2027
  6. HandoverJun 2027

AI insights

SR-JED-02287% conf.
Steel delivery delay threatens roof milestone

PO-2291 structural steel is 11 days behind. Critical path shows roof enclosure slipping 9 days if not recovered.

Recommended: Expedite alternative supplier quote (Al Jazira Steel) and resequence MEP rough-in.