Projects / SR-JUB-005
Industrial · Jubail · Eastern Industrial Partners

Jubail Fabrication Plant

PM Hassan Al-Dosari · 2024-09-12 → 2026-04-30

At Risk
Health score
58
Progress
66%
Plan 75%
Contract value
SAR 163M
Cost to date
SAR 117M
72% of budget
Workers today
175
Open risks
11

Milestones

  1. Mobilisation & enabling worksMar 2025
  2. Substructure completeAug 2025
  3. Superstructure 50%Jan 2026
  4. Building envelope closedJul 2026
  5. MEP testing & commissioningFeb 2027
  6. HandoverJun 2027

AI insights

SR-JUB-00581% conf.
Cost overrun trend in concrete works

Concrete package is 8.4% over budget, driven by rework on Grid C foundations and ready-mix price escalation.

Recommended: Review NCR-114 root cause and lock remaining ready-mix volume under fixed price.
SR-JUB-00589% conf.
Repeated working-at-height observations

4 unsafe observations in 7 days on Hall B roof. Pattern indicates harness anchor shortage.

Recommended: Issue stand-down briefing and procure 20 additional anchor points.