Projects / SR-JUB-005
Industrial · Jubail · Eastern Industrial Partners
Jubail Fabrication Plant
PM Hassan Al-Dosari · 2024-09-12 → 2026-04-30
Health score
58
Progress
66%
Plan 75%
Contract value
SAR 163M
Cost to date
SAR 117M
72% of budget
Workers today
175
Open risks
11
Milestones
- Mobilisation & enabling worksMar 2025
- Substructure completeAug 2025
- Superstructure 50%Jan 2026
- Building envelope closedJul 2026
- MEP testing & commissioningFeb 2027
- HandoverJun 2027
AI insights
SR-JUB-00581% conf.
Cost overrun trend in concrete works
Concrete package is 8.4% over budget, driven by rework on Grid C foundations and ready-mix price escalation.
Recommended: Review NCR-114 root cause and lock remaining ready-mix volume under fixed price.
SR-JUB-00589% conf.
Repeated working-at-height observations
4 unsafe observations in 7 days on Hall B roof. Pattern indicates harness anchor shortage.
Recommended: Issue stand-down briefing and procure 20 additional anchor points.